American Edge Engineers
58 / 73

240 MLD Sewage Treatment Plant, Vasana

Service: MEP Design & Engineering

Vasana, Ahmedabad, GujaratIndustrial / Manufacturing

  • Electrical
  • Power & Control Cable Schedules
  • Voltage Drop
  • Power
  • Control & Instrument Cable and Tray Routes
  • Earthing Calculation & Layout
  • Lightning Protection
  • Lighting Layout & Lux Levels
  • Lighting SLD & LDB Distribution
Sewage treated a day for Ahmedabad Municipal Corporation
240MLD
Earth pits in the grid, one for every major panel and building
59
Earthing grid resistance, against a 1 ohm limit
0.035ohm
Of 50 x 10 mm GI earth strip
2,080m
Electrical drawing sets and schedules, issued 26 November 2025
8
Transformers of 3,150 kVA: two working, one standby
3
Illustrative aerial render of a large sewage treatment plant with rows of aeration tanks, circular clarifiers, a blower building and an electrical substation beside a river
Illustrative image

Project information

A 240 million-litre-a-day sewage treatment plant at Vasana in Ahmedabad, built for Ahmedabad Municipal Corporation. Power arrives at 11 kV to an HT room and a metering kiosk and is stepped down by three 3,150 kVA transformers, two working and one standby, to a power control centre feeding the motor control centres and variable-speed drives of the fine screens, pump houses, air blowers, the centrifuge building, the chlorination room and the dosing tanks, with DG sets, a PLC room and an administration building. The process and the panels are by others; our scope is the plant's cabling, earthing, lightning protection and lighting.

How We Helped 240 MLD Sewage Treatment Plant, Vasana

We issued the power and control cable schedules with their voltage drop calculations, the power, control and instrument cable and tray route layouts, the lighting layout with its lux level calculation and the lighting single-line diagram and distribution boards on 26 November 2025. Earthing: at a measured soil resistivity of 53.08 ohm-m and a 36 kA fault for one second, the earth strip works out at 450 sq mm, 495 sq mm with a 10% corrosion allowance over ten years, so a 50 x 10 mm GI strip is used, 2,080 m of it; each 3 m pipe electrode gives 7.6 ohm, 59 of them in parallel 0.129 ohm, and with the strip the whole grid comes to 0.035 ohm, well under the 1 ohm limit. The layout, revised to R3 in April 2026, gives every pit its job - the HT room, the metering kiosk, each transformer, the DG sets, the power control centre, each MCC and VFD panel, the air blowers, the fine screen panels, the pump houses, the centrifuge building, the chlorination room, the dosing tank, the PLC room and the administration building - with chemical copper and GI earthing pits, test links and two lightning arresters with copper spikes on 25 x 6 mm down conductors.

The brief

What the project needed, and how we answered

  1. 01

    A fault path that keeps people and motors safe.

    At 53.08 ohm-m soil and a 36 kA, one-second fault, the strip works out at 495 sq mm with ten years of corrosion, so 50 x 10 mm GI is used; 59 pipe electrodes and 2,080 m of strip bring the grid to 0.035 ohm.

  2. 02

    Every panel earthed where it stands.

    The layout gives each pit its job - HT room, metering kiosk, transformers, DG sets, PCC, every MCC and VFD, the air blowers, fine screens, pump houses, centrifuges, chlorination, dosing, PLC room and admin building.

  3. 03

    Cables that reach without losing voltage.

    Power and control cable schedules with voltage drop for every feeder, and the power, control and instrument cable and tray routes across the plant.

System by system

What we designed, with the numbers

Power arrives at 11 kV.

Location
Vasana, Ahmedabad, Gujarat
Client
Ahmedabad Municipal Corporation
Capacity
240 million litres of sewage a day
Supply
11 kV to an HT room and metering kiosk; three 3,150 kVA transformers, two working and one standby
Loads
Fine screens, pump houses, air blowers, centrifuges, chlorination and dosing, through MCCs and VFDs

Deliverables

The calculations and drawings behind the design

From November 2025 to April 2026.

  • 2schedules

    Schedules

    Power and control cable schedules with voltage drop (20 and 24 November 2025).

  • 6items

    Layouts

    Power and instrument cable and tray routes, earthing, lightning, the lighting layout with lux levels and the lighting SLD and boards (26 November 2025).

  • 4revisions

    Earthing

    The earthing calculation (19 November 2025) and the earthing layout, R0 to R3 (17 November 2025 to 16 April 2026).

Why EDGE

15+ years of MEP engineering experience

Every discipline, every building type

HVAC, electrical, plumbing and fire protection for new buildings, renovations, fit-outs and franchise programs — one team, one set of coordinated drawings.

Quality checked by engineers

Every drawing set, model and calculation is reviewed by an experienced engineer before it reaches you.

One partner from design to shop drawings

MEP design, energy compliance and shop drawings from one team — fewer handoffs and a single point of contact.

Next step

Have a similar project?

Send one drawing set and see our work on your own project before you decide.

  • Free, no commitment
  • NDA before any files
  • An engineer replies within one business day