American Edge Engineers
33 / 73

Govt. Homeopathy College & Hospital, Kagal

Service: MEP Design & Engineering

Kagal, Kolhapur, MaharashtraHealth + Wellness

  • Environmental Clearance & MEPF Design
  • External MEP Services Location
  • Water Supply & Storage
  • Sewage Treatment
  • Effluent Treatment
  • Storm Water & Rainwater Harvesting
  • Fire Hydrant
  • Rooftop Solar & Solar Hot Water
  • EV Charging
  • Lightning Protection
Main underground domestic water tank, with a second of 86 kL
448kL
Two sewage treatment plants, with an effluent plant for the hospital
420 + 80KLD
Fire water tank for a 150 mm hydrant ring round the buildings
200kL
Transformers, with two DG sets
2 x 630kVA
Rooftop solar PV panels, with more than 150 solar hot-water collectors
130+
Kinds of building on one campus: college, hospital, hostels, staff quarters and nurses' quarters
5
Illustrative aerial render of a college and hospital campus with a college building, a hospital with an ambulance bay, two hostel towers with rooftop solar panels, staff quarters, a running track and playground, parking and tree-lined roads among sugarcane fields, with hills behind
Illustrative image

Project information

A government homoeopathy college and teaching hospital for the Government of Maharashtra at Kagal, in Kolhapur district. The campus brings together a college building of a lower ground and five floors with academic blocks, laboratories, lecture halls, offices and a library; a hospital of a ground and three floors; boys' and girls' hostels; staff quarters of several types, nurses' quarters and the dean's bungalow; playgrounds and open spaces; and parking for the college, the hospital, the hostels and the quarters, linked by 12 m, 9 m and 6 m internal driveways. A campus where people study, are treated and live needs water, power and waste handled for all three at once, and an environmental clearance before it is built. The architecture is the architect's; our scope is the EC layouts and the MEPF design.

How We Helped Govt. Homeopathy College & Hospital, Kagal

We prepared the services layouts from June to August 2026, revising them as the architectural layout changed. Site: the service area set out with space for two 630 kVA transformers and two DG sets, the pump room, the underground tanks, two sewage treatment plants, an effluent treatment plant for the hospital, an organic waste converter and solid-waste handling. Water: underground domestic tanks of 448 kL and 86 kL and a 200 kL fire tank, 3.7 m deep, fed from the bore and tankers through filtration, softening and chlorination, with hydropneumatic pumps and overhead tanks on the buildings. Sewage and effluent: sewer lines from every building to sewage plants of 420 KLD and 80 KLD, a treated-water tank, and the hospital's effluent kept apart through its own treatment plant. Storm water: drains across the campus to the existing storm water lines, with recharge pits for the roofs and the paved surfaces. Fire: a 150 mm hydrant ring with single-headed hydrants and hose boxes round the buildings. Energy and safety for the clearance: more than 130 rooftop solar PV panels and more than 150 solar hot-water collectors of 125 litres on the terraces, EV charging in the college's lower-ground parking and the hostels' stilt parking, and lightning arrestors on the terraces with down conductors to chemical earthing pits.

The brief

What the project needed, and how we answered

  1. 01

    One campus that studies, treats and lives.

    The college, hospital, hostels and quarters share one service area - transformers, DG sets, pump room, tanks, sewage and effluent plants and waste handling - set out on the layout so each block is reached by the shortest runs.

  2. 02

    Hospital effluent kept apart.

    The hospital's effluent goes through its own treatment plant before it joins the sewage, which is treated in plants of 420 KLD and 80 KLD with a treated-water tank.

  3. 03

    An environmental clearance before building.

    The water supply, sewage, storm water, rainwater harvesting, fire hydrant, tank, solar, EV charging and lightning protection layouts were drawn for the clearance submission.

  4. 04

    Energy from the roofs.

    More than 130 solar PV panels and more than 150 solar hot-water collectors of 125 litres are set out on the terraces, and lightning arrestors with down conductors and chemical earthing protect the tall blocks.

System by system

What we designed, with the numbers

College, hospital and housing.

Location
Kagal, Kolhapur
College
Lower ground and five floors: academic blocks, laboratories, lecture halls, offices, library
Hospital
Ground and three floors
Hostels
Boys' and girls' hostels, with stilt parking
Housing
Staff quarters of several types, nurses' quarters, the dean's bungalow

Deliverables

The drawings behind the design

Layouts from June to August 2026.

  • 4revisions

    Services location

    External MEP services location layout, R0 (11 June) to R3 (14 July 2026).

  • 5layouts

    External MEP for EC

    Water supply, sewage, storm water and rainwater harvesting, fire hydrant and UGT (R2, 27 July 2026).

  • 3layouts

    Energy & safety

    Solar hot water and PV (R2), EV charging (R1) and lightning arrestors (R1), 5 August 2026.

Why EDGE

15+ years of MEP engineering experience

Every discipline, every building type

HVAC, electrical, plumbing and fire protection for new buildings, renovations, fit-outs and franchise programs — one team, one set of coordinated drawings.

Quality checked by engineers

Every drawing set, model and calculation is reviewed by an experienced engineer before it reaches you.

One partner from design to shop drawings

MEP design, energy compliance and shop drawings from one team — fewer handoffs and a single point of contact.

Next step

Have a similar project?

Send one drawing set and see our work on your own project before you decide.

  • Free, no commitment
  • NDA before any files
  • An engineer replies within one business day