Maithili Co-operative Housing Society (SK Fortune), Erandwane
Service: MEP Design & Engineering
Erandwane, Pune, MaharashtraResidential
- MEPF Design
- Load Demand
- Transformer & DG Sizing
- Meter Distribution
- Water Demand & Storage
- Drinking Water
- Fire Hydrant & Sprinklers
- Staircase Pressurisation
- EV Charging
- External MEP Services Location Layout
- Internal MEP Services Layouts
- Flats on twelve floors: 24 of two bedrooms, 22 of three and one of five
- 47
- Connected load, 235 kW of maximum demand, on one 315 kVA transformer
- 484kW
- Supply to every flat: 49 connections in all
- 3-phase
- Water a day for 235 residents, with drinking water on its own line
- 31.7kL
- Fire tank for the hydrant and sprinkler pumps
- 75kL
- Plot, with 10,000 sq m of construction
- 1,027sq m

Project information
Fortune Developers are building a new residential building for Maithili Co-operative Housing Society at Erandwane, in central Pune. It rises from a ground floor of entrance lobby, parking and services to twelve residential floors and a terrace, on a 1,027 sq m plot beside a 9 m road, with 10,000 sq m of construction. It holds 47 flats - 24 of two bedrooms, 22 of three and one five-bedroom home - served by two lifts and a fire tower, with mechanical car parking, a pump room and underground tanks at ground level. On a tight city plot, a tall building's tanks, pumps and parking all have to fit at the foot of the tower. The architecture is the architect's; our scope is the MEPF design.
How We Helped Maithili Co-operative Housing Society (SK Fortune), Erandwane
We prepared the calculations and the layouts in June 2026. Power: every flat at 75 W per sq m of carpet area, two 15 HP lifts, the domestic and drinking-water pumps, the water treatment plant, sump and sub-soil pumps, staircase pressurisation, four mechanical car-parking units, street and common lighting, and charging for 20% of the 54 car bays - 11 chargers of 7.2 kW - for 484 kW connected and 235 kW of maximum demand: 261 kVA, or 313 kVA with a 20% margin, on one 315 kVA indoor transformer, with a three-phase supply to every flat - 49 connections in all; and a 160 kVA DG set for the lifts, pumps, parking and common lighting, checked against each motor's starting current. Water: 235 residents at 135 litres a day - 120 litres of domestic and 15 of drinking water on separate pipes - 31.7 kL a day, with domestic, drinking-water and fire tanks underground and on the terrace, and a 75 kL fire tank for the 45 HP hydrant and sprinkler pumps and the jockey pump. Layouts: the transformer, DG set, pump room, tanks and sumps placed on the ground-floor plan, with the tank plan and sections; and the internal services for the first, second, fifth, typical, refuge and terrace floors - plumbing cutouts, service slabs, 150 and 200 mm sunk areas and the fire duct opening into the fire lobby.
The brief
What the project needed, and how we answered
- 01
A tall building on a small city plot.
The transformer, DG set, pump room, underground tanks, sumps and four mechanical car-parking units are all placed at the foot of the tower on a 1,027 sq m plot, with the tank plan and sections drawn so the structure can be set out around them.
- 02
Every flat on a three-phase supply.
Each flat's load was set from its carpet area at 75 W per sq m, and all 47 flats take a three-phase connection - 49 with the two common supplies - on one 315 kVA transformer sized from the 261 kVA demand plus a 20% margin.
- 03
Drinking water kept separate.
Of the 135 litres a resident uses each day, 15 are drinking water with its own tanks, pump and pipes, apart from the 120 litres of domestic water.
- 04
Backup for the lifts and pumps.
A 160 kVA DG set carries the two lifts, the water pumps and treatment plant, the car parking and the common lighting, checked against the starting current of each motor.
System by system
What we designed, with the numbers
Twelve floors on a small plot.
- Location
- Erandwane, Pune
- Plot
- 1,027 sq m
- Construction
- 10,000 sq m
- Floors
- Ground and twelve residential floors, with a refuge floor and a terrace
- Flats
- 47: 24 two-bedroom, 22 three-bedroom, one five-bedroom
- Lifts
- Two of 15 HP, with a fire tower
Deliverables
The calculations and drawings behind the design
Calculations and layouts in June 2026.
484kW connected
Load demand & DG
Flats, lifts, pumps, parking and EV charging, with the transformer, meters and DG set (8 June 2026).
31.7kL a day
Water demand
Domestic and drinking water, tanks and fire water (8 June 2026).
8sheets
Services layouts
External services location and tank details, and internal services for the first, second, fifth, typical, refuge and terrace floors (10 June 2026).
Engineering data
Where the power goes
Every flat at 75 W per sq m of carpet area, then the lifts, pumps, parking and chargers line by line, with the diversity factors applied.
Connected load
484 kW
Everything running, before diversity
- 47 flats282.959%
- EV charging (11)77.816%
- Mechanical car parking6012%
- Lifts & common lighting25.45%
- Pumps & water treatment20.14%
- Pressurisation153%
- Street lighting20%
Share of 483.22 kW
- Maximum demand
- 235 kW
- With 20% margin
- 313 kVA
- Transformer
- 315 kVA
- DG set
- 160 kVA
The 47 flats are under 60% of the load; charging for eleven cars and the four parking machines together add almost half as much again.
Why EDGE
15+ years of MEP engineering experience
Every discipline, every building type
HVAC, electrical, plumbing and fire protection for new buildings, renovations, fit-outs and franchise programs — one team, one set of coordinated drawings.
Quality checked by engineers
Every drawing set, model and calculation is reviewed by an experienced engineer before it reaches you.
One partner from design to shop drawings
MEP design, energy compliance and shop drawings from one team — fewer handoffs and a single point of contact.
Next step
Have a similar project?
Send one drawing set and see our work on your own project before you decide.
- Free, no commitment
- NDA before any files
- An engineer replies within one business day