Plot A, S. No. 79, Kiwale
Service: MEP Design & Engineering
Kiwale, Pune, MaharashtraResidential
- Environmental Clearance & MEPF Design
- Water Demand & Supply NOC
- Drainage NOC
- Sewage Treatment & Reuse
- Load Demand & DG Sizing
- Energy Conservation & ECBC
- Rooftop Solar & Solar Hot Water
- EV Charging
- Lightning Protection
- Basement Ventilation & Dewatering
- External MEP & Plumbing Layouts for EC
- Flats in two towers of 31 and 30 floors, over a basement and four podium levels
- 352
- Connected load, 1,756 kW of maximum demand
- 3,343kW
- Sewage plant for 2,108 people, its water reused for flushing
- 240KLD
- EV car chargers of 7.2 kW, for 30% of the cars
- 155
- Of solar hot water a day, 75 for each flat
- 26,400litres
- Rainwater recharge pits across the plot
- 8

Project information
Plot A of a three-plot development by Ecostar Goel Properties at Kiwale, on the north-western edge of Pimpri-Chinchwad, with 38,432 sq m of construction on an 8,400 sq m plot. A basement, a ground floor and four podium levels hold the parking, with a landscaped podium on top. Above it, building A rises 31 floors with 179 flats - two-bedroom homes of about 700 sq ft carpet and 2.5-bedroom homes of about 826 sq ft - and building B rises 30 floors with 173 two-, 2.5- and three-bedroom flats of about 712 to 956 sq ft, each tower with three lifts, refuge floors and a fire tank floor. A commercial block of ground and first floors with mezzanines and two more floors adds about 12,700 sq ft of carpet area. 352 homes in two 30-floor towers make a heavy load on power, water and fire services, and the environmental clearance has to show each one. The architecture is the architect's; our scope is the EC data and the MEPF design.
How We Helped Plot A, S. No. 79, Kiwale
We prepared the water demand, the energy calculations and the external MEP services location layout in February 2026, revising the water demand to R3 as the commercial population, the sewage plant and the approved layout changed, with the water supply and drainage NOC letters; the external plumbing layouts for the clearance from February to R3 on 26 March; and in March the EV charging, lightning arrester and solar layouts, the basement ventilation and dewatering, and the energy sheet to R3 with the ECBC parameters - the full MEP submission on 27 March 2026. Water: 2,108 people - 1,760 in the homes and 348 in the commercial block - need about 257 kL a day: 167.1 kL of domestic water, 86.2 kL of flushing water and 4.1 kL for the landscape. A 240 KLD sewage plant treats the 228 kL of sewage and sends the treated water back to the flushing and the landscape. Storage: a 405 kL domestic and flushing tank and a 150 kL fire tank below ground for the towers, a 27 kL tank for the commercial block, and a 100 kL fire tank on each tower's terrace, with 100 HP hydrant and sprinkler pumps and a 10 HP jockey pump. Power: 3,343 kW connected and 1,756 kW of maximum demand, on three 630 kVA transformers, with a 500 kVA DG set sized to start the two fire pumps; EV charging for 30% of the cars - 155 points of 7.2 kW - is a third of the connected load. Energy: 182 rooftop solar panels of 675 W - about 123 kW, 7% of the demand, generating about 184 MWh a year - solar collectors for 26,400 litres of hot water a day, 75 for each flat, and timers and drives on the lighting, lifts and pumps. Basement: the 4,225 sq m level, 3.3 m high, gets 49,125 CFM at 6 air changes an hour and 98,250 CFM in a fire, with 15 jet fans and 9 sensors; two sumps of 9 cubic metres, one for each fire zone, take the sprinkler water. Rainwater: eight recharge pits of 2.5 x 2.5 x 2 m with filters.
The brief
What the project needed, and how we answered
- 01
Two towers of more than 30 floors.
A 100 kL fire tank on each tower's terrace backs up a 150 kL tank below ground, with 100 HP hydrant and sprinkler pumps, and a 500 kVA DG set sized to start both fire pumps.
- 02
Charging for 30% of the cars.
155 car points of 7.2 kW add 1,117 kW to the connected load - a third of it - so they were part of the load and the parking layout from the start.
- 03
Water for 2,108 people.
About 257 kL a day: a 405 kL domestic and flushing tank below ground, a 240 KLD sewage plant, and treated water piped back to every flush and the landscape.
System by system
What we designed, with the numbers
Two towers and a commercial block.
- Location
- S. No. 79, Kiwale, Pune
- Plot
- 8,400 sq m
- Construction
- 38,432 sq m
- Building A
- 31 floors, 179 flats: 2-bedroom (about 700 sq ft) and 2.5-bedroom (about 826 sq ft)
- Building B
- 30 floors, 173 flats: 2-, 2.5- and 3-bedroom (about 712 to 956 sq ft)
- Parking & commercial
- Basement, ground and four podium levels; a four-level commercial block
Deliverables
The calculations and drawings behind the design
February and March 2026.
4revisions
Water demand
Water demand, tanks and sewage plant, R0 to R3, with the water supply and drainage NOC letters (February 2026).
4revisions
Energy & ECBC
Load demand, DG set, solar and savings, R0 to R3, with the ECBC parameter sheet (27 March 2026).
8documents
EC layouts
External plumbing to R3, EV charging, lightning arrester, solar, basement ventilation and dewatering (March 2026).
Engineering data
Where the power goes
Every flat at 75 W per sq m and the commercial floors at 150 W, then the lifts, pumps, fans and chargers.
Connected load
3,343 kW
Everything running, before diversity
- 352 flats1,88857%
- EV charging (155 car points)1,116.733%
- Commercial block1414%
- Pumps, STP & OWC87.33%
- Lifts & common lighting58.42%
- Ventilation & pressurisation451%
- Landscape & street lighting50%
Share of 3,341.42 kW
- Maximum demand
- 1,756 kW
- DG set
- 500 kVA
- EV charging
- 1,117 kW connected
- Solar hot water
- 26,400 litres a day
The car chargers add up to a third of the connected load - more than half of what all 352 flats draw.
Why EDGE
15+ years of MEP engineering experience
Every discipline, every building type
HVAC, electrical, plumbing and fire protection for new buildings, renovations, fit-outs and franchise programs — one team, one set of coordinated drawings.
Quality checked by engineers
Every drawing set, model and calculation is reviewed by an experienced engineer before it reaches you.
One partner from design to shop drawings
MEP design, energy compliance and shop drawings from one team — fewer handoffs and a single point of contact.
Next step
Have a similar project?
Send one drawing set and see our work on your own project before you decide.
- Free, no commitment
- NDA before any files
- An engineer replies within one business day