Residential Project, Gat No. 273 P & 281 P, Borhadewadi
Service: MEP Design & Engineering
Borhadewadi, Moshi, Pimpri-Chinchwad (PCMC), Pune, MaharashtraResidential
- Environmental Clearance & MEPF Design
- Load Demand
- Transformer & DG Planning
- Meter Distribution
- Water Demand & Storage
- Drinking Water
- Grey-Water Treatment & Reuse
- Basement Ventilation
- EV Charging
- External & Internal MEP Services Layouts
- Flats in two buildings of seven residential floors
- 81
- Connected load, 254 kW of maximum demand (282 kVA)
- 508kW
- Connections: a single-phase supply to every flat and 3 common
- 84
- Water a day, with drinking water on its own line
- 56kL
- Grey-water plant returning 18 kL a day to the flushing system
- 35KLD
- Plot, with 12,081 sq m of construction
- 2,124sq m

Project information
A residential project on a 2,124 sq m plot at Gat No. 273 P & 281 P, Borhadewadi, near Moshi on the northern edge of Pimpri-Chinchwad, with 12,081 sq m of construction. Two buildings, A and B, rise from a basement and a podium of parking to seven residential floors and a terrace, beside a 9 m road; building A holds 42 flats of one and two bedrooms and building B 39 two-bedroom flats - 81 in all - served by three lifts, with an open space and an amenity space at ground level. Homes of this size on a compact plot need their services kept efficient and their water reused. The architecture is the architect's; our scope is the EC data and the MEPF design.
How We Helped Residential Project, Gat No. 273 P & 281 P, Borhadewadi
We prepared the calculations and the first layouts in March and revised the external layout through June 2026. Power: every flat at 75 W per sq m of carpet area, three 5 HP lifts, the domestic, drinking-water and grey-water pumps, the basement sump, the organic waste converter, basement ventilation, street lighting and charging for 20% of the parking - 8 car chargers of 7.2 kW and 20 two-wheeler chargers of 3.5 kW - for 508 kW connected and 254 kW of maximum demand (282 kVA) on a 315 kVA transformer, on 84 connections: a single-phase supply to each of the 81 flats and 3 common; meter rooms with meter panels and sub-distribution panels for each building; and a 62.5 kVA DG set for the lifts, pumps, ventilation and common lighting, placed above the transformer room. Water: 405 residents at 135 litres a day - 70 domestic, 20 drinking and 45 flushing - and the landscape, about 56 kL a day, with underground tanks of 80 kL domestic, 20 kL drinking and 15 kL raw water, 3 m deep, and terrace tanks on each building, including 25 kL of fire water. Reuse: a 35 KLD grey-water treatment plant between the basement and the ground floor, returning 18 kL a day to the flushing system and watering the landscape, with the surplus to the municipal drain. Floors: the internal services location layout with the plumbing cutouts, service slabs, 150 and 200 mm sunk areas and the electrical and low-voltage slits for every floor and the terrace.
The brief
What the project needed, and how we answered
- 01
Water used twice.
A 35 KLD grey-water plant between the basement and the ground floor treats the waste water and returns 18 kL a day to the flushing system and the landscape, with only the surplus going to the municipal drain.
- 02
Drinking water kept separate.
Of the 135 litres a resident uses each day, 20 are drinking water with their own 20 kL tank, pump and pipes, apart from the domestic and flushing water.
- 03
Every flat on its own meter.
All 81 flats take a single-phase supply, grouped on meter panels in a meter room for each building, with sub-distribution panels for the common services.
- 04
Backup for the common services.
A 62.5 kVA DG set carries the three lifts, the pumps, the basement ventilation and the common lighting, placed above the transformer room.
System by system
What we designed, with the numbers
Two buildings of seven floors.
- Location
- Gat No. 273 P & 281 P, Borhadewadi (Moshi), Pune
- Plot
- 2,124 sq m
- Construction
- 12,081 sq m
- Buildings
- A and B: basement and podium parking, seven residential floors
- Flats
- 81: 42 in A (1 and 2 bedrooms), 39 in B (2 bedrooms)
- Lifts
- Three of 5 HP
Deliverables
The calculations and drawings behind the design
Calculations and layouts from March to June 2026.
2calculations
Water & load
Water demand, tanks and grey water; load demand, meters and DG set (11 March 2026).
3sheets
Internal services
Ground, typical and terrace floors (11 March 2026).
4revisions
External services
R0 (11 March) to R3 (2 June 2026), with the tank details.
Engineering data
Where the power goes
Every flat at 75 W per sq m of carpet area, then the lifts, pumps, fans and chargers line by line.
Connected load
508 kW
Everything running, before diversity
- 81 flats324.564%
- EV charging (28)131.226%
- Basement ventilation173%
- Pumps & OWC16.43%
- Lifts & common lighting15.23%
- Street lighting31%
Share of 507.28 kW
- Maximum demand
- 254 kW
- At 0.9 power factor
- 282 kVA
- Connections
- 84
- DG set
- 62.5 kVA
Charging for 28 vehicles adds 40% to the load of all 81 flats - nearly three times what the lifts, pumps and fans draw together.
Why EDGE
15+ years of MEP engineering experience
Every discipline, every building type
HVAC, electrical, plumbing and fire protection for new buildings, renovations, fit-outs and franchise programs — one team, one set of coordinated drawings.
Quality checked by engineers
Every drawing set, model and calculation is reviewed by an experienced engineer before it reaches you.
One partner from design to shop drawings
MEP design, energy compliance and shop drawings from one team — fewer handoffs and a single point of contact.
Next step
Have a similar project?
Send one drawing set and see our work on your own project before you decide.
- Free, no commitment
- NDA before any files
- An engineer replies within one business day